Skip to content
NOWCAST WXII 12 News at 11pm
Watch on Demand
Advertisement

Forecasting Our Future: Highway 12 Rodanthe Bridge Project

Forecasting Our Future: Highway 12 Rodanthe Bridge Project
construction on the N. C. 12 word anti bridge project. Almost *** decade in the making is nearly complete and it isn't difficult to see why it was so necessary planning for this started in mid 2014. The planning was sparked by the damage done to the existing stretch of highway 12 seen here in blue asphalt, torn apart by hurricanes, Irene and sandy wrinkled with 3 to 4 ft undulations in it or the asphalt just gone. You don't know whether it went out into the ocean or it went out into the sound. Power poles toppled. It leaves quite an impression on you on the power that we're up against, add to that. These images of the beach, eroding and encroaching on the existing stretch of highway. If you travel far enough, you'll find *** former speed limit sign now immersed in the sand. These hot spots were identified as what what options could be taken to relocate the road beach nourishment basically. All options were on the table, bought themselves time after those storms by installing sandbags near the shore line to prevent sinkholes caused by erosion. So these sandbags are five ft wide, two ft thick and 15 ft long. We placed the sandbags in areas where we have overwash that has the potential to undermine the asphalt. It became clear something must be done to find *** long term solution. There have been options in the past and attempts made that were successful of relocating the road in certain areas. But now with the severity of the storms looking for that long term solution, that's why we're going to the bridging option while protecting the existing road and blue crews began to get to work on the new bridge project in red an intricate task with environmental limitations. We need big heavy equipment but yet we could not use barges to work in this area because the water was to shallow. So we had to use *** trestle system, *** temporary bridge system in order to build the permanent bridge and all the while we want to minimize that impact on the sub aquatic vegetation, minimize the impact on any of the adjacent wetlands that we may span across or maybe near the D. O. T. Worked with researchers behind cast using data from previous storms to predict what future impacts to the roadway maybe. So we use climate model projections. It's not like *** weather forecast. Like we're going to say it's going to be nice and cool tomorrow and 72 degrees. But we're looking more 10, 50 years down the road. Use the storms from the past, run them in different scenarios, taking into account new land development, new dune shape, new water contour or excuse me, sound bottom contours and inlet contours and see what are some of the worst case scenarios we could experience for *** bridge. The hope is that planning will accommodate for shifting shorelines and weather events to ensure this bridge is here to stay and make that long term investment With these bridges also being designed for that 100 year service life doesn't mean that we won't have to go out there and do some maintenance, say, in 50 or 75 years, but we won't have to do that in depth, comprehensive maintenance. The Ford Hatch.
Advertisement
Forecasting Our Future: Highway 12 Rodanthe Bridge Project
Construction of the NC-12 Rodanthe Bridge Project almost a decade in the making is nearly complete. It isn't difficult to see why it was so necessary."Planning for this started in mid-2014," Pablo Hernandez, Resident Engineer, NC DOT Division 1.The planning was sparked by the damage done to the existing stretch of HWY-12. Asphalt was torn apart by hurricanes Irene and Sandy."Not wrinkled like a sheet of paper. Wrinkled with a three to four-foot undulations in it or the asphalt just gone. You don't know if it went out into the ocean with it or out into the sound," Hernandez said. Or power poles being knocked down."To see those power lines leaning over or falling into an inlet such as new inlet, it leaves quite an impression on you such as the power that we’re up against.”Add to that, images of the beach eroding and encroaching on the existing stretch of highway.If you go far enough, you'll find a former speed limit sign now immersed in the sand. The DOT bought themselves time after those storms by installing sandbags near the shoreline to prevent sinkholes caused by erosion. "These sandbags are five feet wide, two feet thick and 15 feet long. We place the sandbags in a place where we have overwash with the potential to undermine the asphalt."It became clear something must be done to find a long-term solution. "There have been options in the past and attempts made that were successful at relocating the road in certain area but now with the severity of the storms looking for that long-term solution, that’s why we’re going to the bridging option.”While protecting the existing road, crews began to get to work on the new bridge project. That's an intricate task with environmental limitations."We need big heavy equipment but yet we could not use barges in the area because the water is too shallow. So we had to use a temporary bridge system to build the permanent bridge. All the while we want to minimize the impact on the subaquatic vegetation. Minimize the impact on adjacent wetlands we may span across or be near. So that’s the challenge.”The DOT worked with researchers to hindcast, using data from previous storms to predict what future impacts to the roadway may be."We know that storms are getting more frequent and intense and we have to start to think about the future so we use climate model projections. It’s not like a weather forecast it'll be cool and 72 degrees but we’re looking more 10-15 years down the road.”"Use the storms from the past, run them in different scenarios taking into account new land development, dune shape and sound bottom contour and inlet contour and see what are some of the worst case scenarios we could experience for a bridge.”The hope is that planning will accommodate for shifting shorelines and weather events, to ensure this bridge is here to stay."Being designed for that 100-year service life. Doesn't mean we’re not going to have to go out there and do some maintenance in 50 or 75 years but we won’t have to do that in-depth comprehensive maintenance."

Construction of the NC-12 Rodanthe Bridge Project almost a decade in the making is nearly complete. It isn't difficult to see why it was so necessary.

"Planning for this started in mid-2014," Pablo Hernandez, Resident Engineer, NC DOT Division 1.

Advertisement

The planning was sparked by the damage done to the existing stretch of HWY-12. Asphalt was torn apart by hurricanes Irene and Sandy.

"Not wrinkled like a sheet of paper. Wrinkled with a three to four-foot undulations in it or the asphalt just gone. You don't know if it went out into the ocean with it or out into the sound," Hernandez said.

Or power poles being knocked down.

"To see those power lines leaning over or falling into an inlet such as new inlet, it leaves quite an impression on you such as the power that we’re up against.”

Add to that, images of the beach eroding and encroaching on the existing stretch of highway.

If you go far enough, you'll find a former speed limit sign now immersed in the sand.

The DOT bought themselves time after those storms by installing sandbags near the shoreline to prevent sinkholes caused by erosion.

"These sandbags are five feet wide, two feet thick and 15 feet long. We place the sandbags in a place where we have overwash with the potential to undermine the asphalt."

It became clear something must be done to find a long-term solution.

"There have been options in the past and attempts made that were successful at relocating the road in certain area but now with the severity of the storms looking for that long-term solution, that’s why we’re going to the bridging option.”

While protecting the existing road, crews began to get to work on the new bridge project. That's an intricate task with environmental limitations.

"We need big heavy equipment but yet we could not use barges in the area because the water is too shallow. So we had to use a temporary bridge system to build the permanent bridge. All the while we want to minimize the impact on the subaquatic vegetation. Minimize the impact on adjacent wetlands we may span across or be near. So that’s the challenge.”

The DOT worked with researchers to hindcast, using data from previous storms to predict what future impacts to the roadway may be.

"We know that storms are getting more frequent and intense and we have to start to think about the future so we use climate model projections. It’s not like a weather forecast it'll be cool and 72 degrees but we’re looking more 10-15 years down the road.”

"Use the storms from the past, run them in different scenarios taking into account new land development, dune shape and sound bottom contour and inlet contour and see what are some of the worst case scenarios we could experience for a bridge.”

The hope is that planning will accommodate for shifting shorelines and weather events, to ensure this bridge is here to stay.

"Being designed for that 100-year service life. Doesn't mean we’re not going to have to go out there and do some maintenance in 50 or 75 years but we won’t have to do that in-depth comprehensive maintenance."